RUL Estimation
CHL-02
Chiller 02
CHL-02 · Utility · UT-1
Health Score44/100
RUL Estimate21 days
Confidence12–34 days
Est. Service Date10 Dec 2026
Action Required
This machine's RUL is below 60 days. Schedule maintenance or inspection immediately.
Health Degradation Projection — Chiller 02
Health Trend (Past 30 days) — Chiller 02
Machine RUL Ranking
| # | Machine | Area | Health | RUL (days) | Confidence Range | Status | Est. Service |
|---|---|---|---|---|---|---|---|
| 1 | Chiller 02 CHL-02 | Utility | 44 | 21 | 12–34 | Urgent | 10 Dec |
| 2 | Air Compressor 01 CMP-01 | Utility | 62 | 48 | 35–60 | Urgent | 6 Jan |
| 3 | Cooling Pump 04 PMP-04 | Utility | 58 | 64 | 40–90 | Plan | 22 Jan |
| 4 | Curing Oven 01 OVN-01 | Paint | 71 | 130 | 90–170 | OK | 29 Mar |
| 5 | Welding Robot 07 WLD-07 | Assembly | 77 | 180 | 140–220 | OK | 18 May |
| 6 | Injection Molding 03 INJ-03 | Molding | 81 | 210 | 170–250 | OK | 17 Jun |
| 7 | Hydraulic Press 05 PRS-05 | Stamping | 88 | 320 | 260–380 | OK | 5 Oct |
| 8 | Conveyor 11 CNV-11 | Assembly | 93 | 410 | 350–470 | OK | 3 Jan |